NFPA 70E requires a documented meeting between the host and contract employer if the host has knowledge of hazards covered by this standard. The specific language is: 110.3 Host and Contract Employers’ Responsibilities. (C) Documentation. Where the host employer has knowledge of hazards covered by this standard that are related to the contract employer’s work, there shall be a documented meeting between the host employer and the contract employer. This week's question - Regardless of whether you are the host or contract employer: Do you have a documented meeting between the host and contract employer? Yes No Depends Doesn't Apply Us |
|
| Author: | Voltrael [ Mon May 16, 2016 9:08 am ] |
| Post subject: | Re: Documented Meeting Between Host and Contract Employer |
The contractors I have worked with since starting with my current employer have been working here for years, so it hadn't occurred to me to have a documented meeting with them. |
|
| Author: | willcoc [ Tue May 17, 2016 7:01 pm ] |
| Post subject: | Re: Documented Meeting Between Host and Contract Employer |
I would think that our work permits would provide this type of documentation. No contractor work without a permit. If an EEWP is needed, then it is an additional document to cover that aspect. |
|
| Author: | Voltrael [ Thu May 19, 2016 5:09 am ] |
| Post subject: | Re: Documented Meeting Between Host and Contract Employer |
Oh technically before every job (contractor and employee) a form needs to be filled out detailing all safety concerns for the job. For any jobs I have with a contractor, I review it with them and sign the form. Guess that might fulfill the requirement. |
|
| Author: | PaulEngr [ Fri May 20, 2016 10:16 am ] |
| Post subject: | Re: Documented Meeting Between Host and Contract Employer |
I hate to say it but at one time it seemed like safety rules were pretty uniform from one site to another. The only thing that really varied was enforcement. I haven't ever tried to do it but I can almost develop a checklist of items that vary from one site to another (and sometimes even within the same site). It is no longer really practical or possible to have a single set of work rules that work universally for contractors, so the contractor/host meeting has become critical to make sure that those subtle differences are passed along. |
|